A project manager has been overwhelmed with problems on his project. He would like to identify the root cause of the problems in order to determine where to focus his attention. Which of the following tools would be BEST for the project manager to use?
A、Pareto chart
B、Conflict resolution techniques
C、Fishbone diagram
D、Trend analysis