The project manager in a matrix organization is starting a new project , and identified a critical resource in the organization's staffing inventory. This resource is currently working for the functional manager, and is committed to another project. What technical should the project manager use?
A、Acquisition
B、Pre-assignment
C、Negotiation
D、Virtualization