A consulting firm was awarded a mega credit card processing system revamping project. Having failed to deliver the expected product within budget the last two mega projects, what approach should the consulting firm take in the initial stages of the project to avoid past failures?
A、Allow employees to work overtime.
B、Move its best employee from smaller projects to this mega one
C、Divide the project into multi-phases project
D、Hire additional technical employees from oversea market