The project manager of a complex project is working on planning risk response activities. As an expert in risk management, the project manager considers risk transfer options. What is the primary effect of risk transference?
A、Project manager will not be in charge of the project production.
B、Additional cost may be paid to who will be in charge of the risk.
C、May be transfer the project management responsibilities to who will be in charge of the risk
D、Project manager cannot do risk transfer