A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(  ).
A.a(chǎn)ssign  change  tasks to project  members
B.call  a meeting of the  configuration  control  board
C.change  the  scope  baseline
D.postpone the modification until a separate enhancement project is funded after  this project  is completed according to the  original  baseline